Insight: Why the Electronic Communications Code is key for Speeding up the UK’s connectivity
Written by Darren Zitren, partner and head of network estate management at Cluttons,
A few weeks ago the Government published its long-awaited response to the review and consultation (Jan 2021) concerning the 2017 Electronic Communications Code (‘the ECC’) – legislation which governs telecommunications agreements, whether for fixed line or wireless infrastructure, across the UK.
Whilst launched with the intention of simplifying and speeding up the roll out of critical and much needed communications infrastructure and technologies across the UK; since the implementation of the ECC this roll out has been hugely delayed and an industry has been left divided and fraught with dispute over access, contracts and associated payments.
As a leading advisor on telecommunications and connectivity for the real estate industry, specialising in wayleaves and network strategy, we have examined the reforms announced, reviewed our own research into the topic and added our verdict.
The reforms
The Government has rightly highlighted that the Electronic Communications Code has a key role to play in the rollout of gigabit-capable networks. Last week’s published revisions to the ECC were a step in the right direction, particularly when it comes to clearing the pathway for operators and fibre service providers to get the job done and lay the crucial infrastructure.
Within the proposed amendments to the ECC, there are many encouraging aspects for the marketplace and which reaffirm the UK Government’s commitment to a connected Britain:
- The launch of a new process allowing for an agreement to be imposed by default whereby a landowner has been unresponsive to three sets of notices by the operator
- Operators already in situ can now renew their expired agreements with the landowner directly to speed up the process
- Sharing of existing apparatus to be made a specific right, albeit this is a bare right that will still need to be specifically agreed or acquired
- The amending of the statutory framework of 1954 Act renewals to closer align with the ECC
- Operators and landowners alike will be able to apply for interim orders on renewal negotiations meaning that operators can now seek modifications to an existing agreement, and determine an interim rent from the Tribunal to unlock any potential rent reduction
However, there were some less positive parts within the bill such as:
- The modification of existing agreements during the term are still not to be permitted unless consensually agreed
- There will be no additional formal fast-track process or any further statutory time limits imposed for dealing with cases beyond the current rule that applications on new sites will be dealt with within 6 months. The Government feels the changes it is making will negate any need for this. We are less positive and will have to wait to see if this is indeed the case